A P P E N D I X G
G-1
LP 100R PC CARTRIDGE INSTALLATION
Packing list
1 PC drum 1 2 PC cleaning unit 1
3 Cleaner blade 1
Note1: Before starting the installation, turn the printer OFF.
1. Install the new PC drum to the stops in the
cleaning unit as shown in Figure G-1.
Note: To avoid damage to PC drum
surface, avoid direct contact to surface.
Note: Use the supplied cleaning pad or
other suitable item to shield the PC drum
from contact damage and prolonged
exposure to light.
2. Re-install the PC cartridge in the EP drawer as
shown in Figure G-2.
Figure G-2
1
2
PC DRUM
3
Figure G-1